ALL Verk ehf. has signed contracts for three new construction projects in Ísafjörður. The projects involve a new reception building at Hrafnatangi, renovations to the laboratory department of the Westfjords Health Institution and replacement of the roof of the town’s Administration Building.
According to public tender and award documents, ALL Verk’s bids for the three projects total approximately ISK 447.2 million.
The company announced the contracts on 22 September and said work was scheduled to begin at the end of September.
ISK 326 million reception building at Hrafnatangi
The largest project is the construction of a new reception building at Hrafnatangi in the port area of Ísafjörður.
Four bids were submitted for the project. On 16 July, the Ísafjarðarbær municipal executive committee approved ALL Verk’s bid of ISK 326,165,756. The port authority had previously recommended contracting the company as the lowest bidder.
The new building will provide facilities for tourists, potential vendors and customs authorities. It will also serve as a customs checkpoint at the pier for passengers entering Iceland through the port.
The project is part of the continued development of Ísafjörður’s port area. The Ísafjarðarbær port budget had previously stated that design work was under way on a passenger reception building at Sundabakki, alongside other projects intended to improve facilities and safety amid increased traffic through the port.
The municipal executive committee approved ALL Verk’s bid this summer and also agreed that the project should be included in the budget preparations for 2027.
HVEST laboratory department to be renovated for ISK 78.3 million
ALL Verk has also won the contract to renovate the laboratory department of the Westfjords Health Institution in Ísafjörður.
On 10 September, Framkvæmdasýslan – Ríkiseignir (FSRE) announced that ALL Verk’s bid had been selected and accepted, creating a binding contract between the parties. The bid amounted to ISK 78,271,257, including value-added tax.
The project involves extensive renewal of the regional hospital’s blood-testing department. Spaces currently housing the laboratory, cold storage, dry storage and kitchen facilities will be refurbished.
The work includes demolishing existing walls, stairs and fixtures; relocating and constructing new walls; and fully renewing the fittings. Fire protection improvements will also be carried out.
The tender was advertised in June and bids were opened on 13 August. FSRE subsequently confirmed in September that ALL Verk had submitted the most advantageous bid under the tender’s award criteria.
Administration Building roof to be replaced for ISK 42.8 million
The third project is an extensive renewal of the roof of the Administration Building in Ísafjörður.
ALL Verk submitted the lowest bid, ISK 42,764,200, compared with a cost estimate of ISK 79,116,000. The bid was therefore equivalent to just 54.1% of the estimate.
The project involves a complete roof replacement, including the metal roofing, roofing felt, gutters, plywood and insulation. General replacement of the rafters was not included, although several were known to be in poor condition because of moisture. Leaks had also occurred in several parts of the building.
On 27 August, the Ísafjarðarbær municipal executive committee approved payment of the municipality’s share of the project. According to the committee minutes, completion is scheduled for 30 November 2026.
Ísafjarðarbær owns a 28.574% share of the Administration Building. Based on the bid amount, the municipality’s share of the cost will be approximately ISK 12.2 million.
Total bid value: ISK 447.2 million
According to the available documents, ALL Verk’s bids for the three projects are:
- Reception building at Hrafnatangi: ISK 326.2 million
- HVEST laboratory department renovations: ISK 78.3 million
- Administration Building roof: ISK 42.8 million
The combined value is therefore approximately ISK 447.2 million.
ALL Verk said it was grateful for the trust shown in the company through the projects and looked forward to starting the work and cooperating with the parties involved.