HomeNewsKópavogur’s Selection of ÞG Verktakar for Kórinn Stadium Voided

Kópavogur’s Selection of ÞG Verktakar for Kórinn Stadium Voided

Iceland’s Public Procurement Appeals Committee has annulled Kópavogur’s decision to select the bid from ÞG verktakar ehf. for the design and construction of a new football stadium at Kórinn.

The case was discussed at a meeting of Kópavogur’s procurement committee on 28 September, where the municipality’s legal services presented the committee’s ruling in case no. 22/2026. The procurement covers a new spectator stand and service building, as well as a heated artificial-turf pitch with floodlighting and associated works.

In April, Kópavogur decided to select ÞG verktakar’s bid following competitive dialogue with ÞG verktakar and Ístak. Ístak appealed the decision to the Public Procurement Appeals Committee, automatically suspending the conclusion of the contract.

Only 0.99 points separated the companies

According to the appeals committee’s documents, ÞG verktakar received 78.56 points overall, while Ístak received 77.57 points. The difference was therefore just 0.99 points.

Ístak argued, among other things, that its score for certain aspects of the quality assessment had been reduced between its initial proposal and final bid, despite the company’s view that it had addressed comments from Kópavogur’s evaluation and dialogue committee.

When the appeals committee first considered suspending the conclusion of the contract in May, its specialist concluded that, based on the available documents, it was difficult to see how Ístak’s final bid could be considered worse than the company’s earlier proposal in the areas under dispute.

The committee found that the difference in the scores was sufficient to potentially change the ranking of the bids, and that there were substantial grounds to conclude that the Public Procurement Act may have been breached. It therefore rejected Kópavogur’s request to lift the suspension of the contract conclusion.

Decision now annulled

The final outcome of the case was presented to Kópavogur’s procurement committee at the end of September.

The committee’s minutes state that Kópavogur’s decision to select the bid was annulled. In a recorded statement by Orri Thor Eggertsson, a representative of the Social Democratic Alliance, he said the appeals committee had identified shortcomings in transparency and the reasoning behind the evaluation of the bids. The statement also says that the committee considered Kópavogur liable for damages in the case.

The majority of the Independence Party and Progressive Party on the procurement committee agreed that it was important to learn from the ruling and that public procurement must meet requirements for transparency and equal treatment. However, the majority rejected criticism that municipal staff, the procurement committee and independent evaluators had not acted in good faith, and said transparency would be ensured regarding the next stages of the case.

Contract worth nearly ISK 2 billion

The appeals committee’s earlier decision states that Kópavogur described the proposed contract as being worth nearly ISK 2 billion.

However, the initial cost estimate for developing the competition pitch at Kórinn was higher. It amounted to ISK 2,204,708,910 including VAT, comprising approximately ISK 1.917 billion in construction costs and ISK 287.6 million for design, project management and supervision. The construction cost included a 20% contingency allowance of just over ISK 319.5 million.

Kópavogur had approved an investment of ISK 2 billion in the project.

Stand, service building and heated pitch

The project involves designing and constructing a two-storey spectator stand with a service building at HK’s main ground in the Kórahverfi neighbourhood.

It also includes a fully equipped heated artificial-turf pitch with floodlighting, together with landscaping, site works and associated structures. The competitive dialogue covered architectural and engineering design, construction of the stand and its completion, development of the pitch and completion of the surrounding site.

The earlier preliminary design provided for a 1,192.5-square-metre stand building. ASK arkitektar and HANNA verkfræðistofa contributed to the preliminary design on which the original cost estimate was based.

Next step remains unclear

In April, Kópavogur authorised the conclusion of a contract with ÞG verktakar. However, the municipal council’s approval was expressly conditional on the outcome of the Public Procurement Appeals Committee’s proceedings.

With the decision annulled, that outcome can no longer provide the basis for concluding the contract.

The procurement committee’s minutes do not state which route Kópavogur intends to take next in the procurement process. Committee members called for information about the next steps, while representatives of the governing majority said transparency in communicating the continuation of the case would be ensured.

Project details

  • Client: Kópavogur
  • Project: Design and construction of a football stadium at Kórinn
  • Procurement procedure: No. 2402380
  • Bidders in the competitive dialogue: ÞG verktakar and Ístak
  • Initial result: ÞG verktakar, 78.56 points; Ístak, 77.57 points
  • Initial project cost estimate: Approximately ISK 2.205 billion
  • Current status: Kópavogur’s selection of ÞG verktakar’s bid has been annulled

Originally published in Icelandic on BYGGINGAR.IS.