Alefli ehf. is constructing a new 1,200-square-metre substation for Veitur at Sægarðar 1 in Sundahöfn, Reykjavík. Known as A13, the facility will be an important part of the port area’s electricity infrastructure and is intended, among other things, to enable Faxaflóahafnir to provide shore power to ships at berth.
The two-storey substation will be built from cast-in-place concrete, with a lightweight roof, external insulation and coloured aluminium cladding.
According to Alefli, the building will have a footprint of approximately 750 square metres, while the upper floor will measure around 450 square metres. Its total floor area will therefore be approximately 1,200 square metres.
Alefli ehf. is the main contractor for the building, while Veitur is carrying out the project.
Rendering: T.ark
Three power transformers and 60 MVA capacity
The new substation will be equipped with three power transformers and will have a total capacity of 60 MVA.
It will connect to Veitur’s electricity network and serve the needs of the port area, nearby businesses and new development.
The facility will contain electrical equipment for three voltage levels: 132 kV, 33 kV and 11 kV.
According to Veitur, the station’s 132 kV switchgear will not use SF6 gas.
Photo: Alefli ehf.
Extensive high-voltage works
Alongside construction of the substation, Veitur is installing new high-voltage cables and building connections to the electricity network.
The project includes the installation of approximately 9,090 metres of 132 kV cables and 6,600 metres of 33 kV cables.
Precast concrete duct banks are being used to facilitate the installation of high-voltage cables in an urban environment and reduce disruption.
According to Veitur, this method can reduce the extent of excavation areas by 60–70% compared with conventional construction.
Photo: Alefli ehf.
Energy transition in Sundahöfn
In 2024, Veitur and Faxaflóahafnir signed an agreement for the delivery of up to 16 MW of electricity for port operations.
The new substation will be a key part of that development and is intended to provide the foundation for shore connections for ships in Sundahöfn.
Connecting ships to electricity from shore will make it possible to reduce their use of auxiliary engines while berthed, thereby reducing pollution.
The increased electricity capacity will also serve companies in the port area, including for charging electric work equipment and larger vehicles.
Photo: Alefli ehf.
Several companies involved
In addition to Alefli, several Icelandic design and contracting companies are involved in the project.
T.ark is responsible for designing the substation. Verkís is handling the design and consultancy for the electrical equipment, while Lota Verkfræðistofa is designing the duct banks for the high-voltage cables.
PK Verk ehf. has carried out the first phase of duct-bank installation.
Work on cable installation in the area will continue in 2026 and 2027.
The new substation is scheduled to enter service in spring 2029. However, Alefli’s contract value and the final total cost of the works have not been confirmed in public documents reviewed by BYGGINGAR.IS.
BYGGINGAR.IS has previously reported on the project under the headline “An important building rises in Sundahöfn.”
Originally published in Icelandic on BYGGINGAR.IS.