Construction of a new rescue centre measuring just over 1,100 square metres at Borg in Grímsnes is progressing according to schedule. HR smíði is responsible for the construction, and the building’s glulam structural frame, supplied by Límtré Vírnet, was erected on Friday, 23 October. The building is scheduled to be weather-tight by December 2026.
The new rescue centre is being built at Þinggerði 1 in Borg as a joint project by the Grímsnes- and Grafningshreppur municipality, Árnessýsla Fire and Rescue Services and the Tintron Rescue Team.
According to information from the municipality, the building’s concrete floor slab was poured almost one month before the structural frame was erected.
Glulam frame and steel-clad mineral wool panels
The building’s structural frame is made from glulam, and work is currently under way to complete it before the cladding is installed.
The walls and roof will be clad with steel-clad mineral wool panels, while the building’s intermediate floor will also be made from glulam.
The building will have dark-grey cladding and red vehicle doors, pedestrian doors and windows, in keeping with the appearance of other rescue and fire stations in South Iceland.
Two arched rooflights will be installed along the roof ridge to provide daylight to the building’s vehicle halls.
Facilities for the fire service and rescue team
The rescue centre will measure just over 1,100 square metres and will be divided into two main sections: one for Árnessýsla Fire and Rescue Services and the other for the Tintron Rescue Team.
Each section will have its own vehicle hall and operational facilities on two floors.
The Árnessýsla Fire and Rescue Services section will include changing rooms with showers on the lower floor, along with a kitchenette and meeting room on the upper floor.
The Tintron Rescue Team’s facilities will include a lounge, changing rooms and equipment rooms on the lower floor. The upper floor will provide space for meetings, incident management and the team’s youth programme.
Separate technical building with backup generator
In addition to the main building, a small, detached technical building will be constructed on the site.
It will house utility connections, an electrical distribution board and a backup generator intended to ensure the centre can continue operating during power outages.
The technical building will also contain an air compressor serving both the fire service and the rescue team.
Borg’s first fire station
The new rescue centre will include Borg’s first fire station.
The aim of the project is to improve facilities for emergency responders, reduce response times and increase safety for residents, owners of holiday homes and tourists in the area.
HR smíði is scheduled to hand over the building as a weather-tight shell in December 2026.
The municipality’s latest information does not state HR smíði’s contract value, the project’s total cost estimate or when the building’s final completion will be finished.