Utility Work Delays Blasting at Fannborg Site

Blasting for the redevelopment of Fannborg in central Kópavogur will not begin until November at the earliest, according to the latest construction schedule. The work had previously been expected to start in October.

Drainage lines, electricity cables and fibre-optic cables must be relocated and connected before drilling for the blasting can begin. Blasting is expected to continue for three to four months during this phase of the project.

Kópavogur Municipality reported the revised status of the work on 21 October, and the contractor, Mannverk, published updated information on 27 October. According to the municipality, blasting can begin no earlier than around the middle of November. A final start date has not been set.

Utility work must be completed first

Earthworks are already under way at the Fannborg site. The work includes removing loose soil from the bedrock and moving utilities outside the planned building area.

Connections for drainage lines, electricity cables and fibre-optic cables must be completed before the next phase can begin. According to the contractor, these connections are expected to be finished before excavation of the loose soil and drilling for blasting start.

In September, the expectation was that blasting could begin in approximately four weeks, during the latter half of October. It is now clear that this phase will start later.

Rock breaking to continue in the coming weeks

Although blasting has not started, earthworks will continue at the site. This includes breaking rock with an excavator in short periods as required.

According to Kópavogur Municipality, rock breaking will take place on weekdays between 7:30 and 18:00. It is not always possible to predict precisely when the work will be needed, but it can be expected intermittently over the coming weeks.

Vibration monitors to be installed

Before blasting begins, vibration monitors will be installed on nearby buildings to monitor the effects of the work.

According to the project specifications, the particle velocity caused by blasting may not exceed 15 millimetres per second.

Blasting is expected to begin cautiously while specialists assess the characteristics of the bedrock and adapt the construction methods.

Residents and others who may be affected will receive a separate notification about planned blasting approximately one week in advance.

Blasting expected to last three to four months

Under the latest schedule, blasting is expected to continue for three to four months during this phase of the redevelopment.

It is not yet known whether the revised blasting start date will affect the overall construction period or the planned completion date.

Mannverk is carrying out the work at Fannborg, where a new town centre is being developed in Kópavogur.