An Italian construction company that Kópavogur Municipality plans to claim ISK 3.9 billion from over breaches of contract during the reconstruction of Kársnes Primary School has been under a payment moratorium for more than two years. The company’s Icelandic subsidiary was declared bankrupt at the end of last year.
Kópavogur Municipality is seeking full compensation for the contractor’s breaches in the construction of Kársnes Primary School. In a press release issued in the middle of last month, the municipality said it intended to claim ISK 3.9 billion from Italian contractor Rizzani de Eccher over breaches of contract during the project.
Kópavogur terminated its contract with Rizzani de Eccher in 2023 because of breaches and defects in the work. The project was supposed to be nearing handover at that point, but it was only half complete. Another contractor took over and completed the work, and the school opened in autumn 2025.
Kópavogur’s cost for Kársnes Primary School is close to ISK 9 billion—more than double the original cost estimate. Part of the additional cost can be attributed to the Italian contractor’s failures.
However, the municipality’s announcement did not mention that Rizzani de Eccher has been under a payment moratorium in Italy in recent years. The company’s Icelandic subsidiary, Rizzani de Eccher Ísland ehf., was declared bankrupt at the end of last year.
The contractor’s financial position was known
An arbitration tribunal ruled on 3 September 2024 that Kópavogur’s termination of the contract had been lawful and that Rizzani was required to pay the municipality’s legal costs in full.
Kópavogur opened a new case this autumn and spent several months compiling its claim and supporting documents concerning additional costs resulting from the change of contractor, delays and extensive defects in Rizzani de Eccher’s work. The municipality submitted the case to arbitration and to the municipal executive committee in mid-October, saying that the next step would be to pursue full compensation. Kópavogur is seeking payment from the parent company in Italy.
Jóhannes Karl Sveinsson, the lawyer working on the case with Kópavogur Municipality, told the broadcaster’s newsroom that the contractor’s position had become clear soon after the arbitration ruling. Rizzani de Eccher had been under a payment moratorium for several years, he said, but remained in operation and continued to work in various locations, including outside Italy.
Photo: RÚV / Kristinn Þeyr
Jóhannes said it was uncertain what the final claim would be and whether Rizzani de Eccher had the ability to pay, given its financial position.
“The company has not been paying claims because it is under a payment moratorium, but it is operating, so I assume it is paying wages and taxes,” he said.
It therefore remains to be seen how much Kópavogur Municipality will recover against its claims.
BYGGINGAR.IS previously reported that Kársnes Primary School cost ISK 8.73 billion and that the compensation claim against the contractor amounted to ISK 3.89 billion.
Originally published in Icelandic on BYGGINGAR.IS.