The 330-metre-long, 2,000-tonne superstructure for the Ölfusá Bridge has been moved from the river’s east bank to the west bank. The operation went very well, and a video describes and documents the work.
Powerful hydraulic jacks pulled the bridge deck forward along specially designed pulling rails. The superstructure rested on pads and slid across smooth steel plates, preventing damage to the surfaces of the steel beams.
The jacks moved the bridge deck half a metre at a time. Under the best conditions, it was estimated that the deck could be moved at a rate of 10 metres per hour. The entire operation, however, took considerably less time than originally estimated.
A large temporary mast was installed on top of the bridge deck to support it as it was pulled across the river. Steel cables extending from the mast supported the front end of the deck throughout the move.
An earlier BYGGINGAR.IS report covered the development of the Ölfusá Bridge steel structure.