The estimated final cost of the new Bíldudalsskóli is ISK 151 million higher than originally planned. An analysis by Vesturbyggð municipality found that design, consulting and supervision costs were underestimated, additional works were approved without securing sufficient budget authority, and monitoring of the project’s cost development was inadequate.
Vesturbyggð’s town council approved a budget amendment related to the overrun on 22 September. The municipal executive committee had approved the amendment the previous day and referred it to the town council.
The municipality says that its cost assessment, planning and follow-up of the project’s total cost were not sufficiently accurate. Vesturbyggð also states that the analysis did not reveal any unnecessary work or careless use of funds.
Cost deviations were not identified until now
According to the municipal executive committee’s statement, the costs of design, consulting, supervision, tender documentation and construction inspection were underestimated during the construction period, which began in 2023.
Additional works were also approved while construction was under way without the appropriate budget authority being secured. The committee says that monitoring of cost development was inadequate, meaning that the cost deviations were not identified until now.
Vesturbyggð’s announcement also says that delays to the project required budget allocations and grants to be moved between financial years as the work progressed.
ISK 151 million taken from other projects
The overrun will not be covered by a new investment appropriation on top of the existing budget. Instead, other municipal investment projects will be postponed or reduced.
According to the municipal executive committee, projects worth a total of ISK 159.9 million will be moved or postponed. They include:
- the tender for demolishing Straumnes;
- the purchase of timber for Bíldudalur Harbour;
- equipment purchases;
- street and public-space works;
- fibre-optic installations; and
- work at the Patreksfjörður Community Centre.
The amendment for Bíldudalsskóli amounts to ISK 151 million and is intended to secure funding to complete the project.
Lowest school construction bid was already ISK 90.6 million above estimate
The project’s cost development had already attracted attention when construction of the school was put out to tender in 2024.
The tender estimate was ISK 375,897,217, but all three bids exceeded that amount. Arctic North submitted the lowest bid, at ISK 466,500,420. Hrífunesskógar bid ISK 479,287,089, while Land og verk bid ISK 494,219,637. Arctic North’s bid was therefore approximately ISK 90.6 million, or 24%, above the estimate. The town council approved entering into a contract with the lowest bidder.
This comparison should, however, be distinguished from the new ISK 151 million deviation. According to Vesturbyggð, the new figure is based on an assessment of the project’s total cost, including design, consulting, supervision and additional works. The ISK 375.9 million figure was the estimate for the tender covering construction of the school building.
Costs increased during construction
Further unforeseen expenses emerged after construction began.
In January 2025, soil investigations showed that soil replacement beneath the school was necessary. The cost was then estimated at ISK 25–30 million, and the town council later approved an amendment involving an ISK 28 million change related to the work.
In July 2025, a second amendment was submitted, providing for ISK 87.3 million for fixtures, equipment and the heating system at Bíldudalsskóli.
Later that year, an additional ISK 16.5 million was approved for furniture and loose equipment for the school.
School opened later than originally planned
The tender documents originally set completion for 15 July 2025, and there were hopes that school operations could begin in the new building in autumn 2025.
The school was formally opened in May 2026. Construction began late in 2024, while the project’s preliminary design began in 2023.
Arctic North contractor; Arkibygg lead consultant
Arctic North, which also operates under the name Arno.is, carried out construction of the school building. Arkibygg was Vesturbyggð’s lead consultant and designed the school together with GINGA teiknistofa.
Ástríður Birna Árnadóttir of Arkibygg was lead architect, and Stefanía Helga Pálmarsdóttir was design and project manager. Teknik handled structural and building-services design, Verkhönnun handled electrical design, Myrra hljóðstofa handled acoustics, and Landmótun handled landscape design.
Vesturbyggð to change its procedures
The municipality says it has conducted a detailed review of the preparation, execution and cost development of Bíldudalsskóli. The analysis demonstrated a need for improvements in project preparation, budgeting, budget-authority management and follow-up.
Vesturbyggð plans, among other measures, to increase cost control, improve information sharing and conduct more regular reviews of the financial position of larger construction projects. The aim is to make cost estimates more realistic and ensure that deviations are identified earlier.
Gerður Björk Sveinsdóttir, mayor, says it is important to learn from the project and for the municipality’s managers to ensure that the agreed improvements are implemented.
Key figures
- Deviation from the original estimate: ISK 151 million.
- Original estimate for the 2024 construction tender: ISK 375.9 million.
- Arctic North bid: ISK 466.5 million.
- Soil replacement: approximately ISK 28 million.
- Fixtures, equipment and heating system: ISK 87.3 million.
- Furniture and loose equipment: ISK 16.5 million.
- Other investment projects to be postponed or reduced because of the new amendment: ISK 159.9 million.
BYGGINGAR.IS previously reported that all bids for the Bíldudalsskóli site were rejected and that the lowest bidder subsequently withdrew.
Originally published in Icelandic on BYGGINGAR.IS.