Borgarverk completes roadworks in Melahverfi III

Road construction in Melahverfi III in Hvalfjarðarsveit has been completed. The work included paving roads and paths, installing lighting and laying all utility networks within the project area.

This is stated in the minutes of Hvalfjarðarsveit’s Infrastructure and Construction Committee meeting on 22 September 2026. The project was a collaboration between Hvalfjarðarsveit municipality, Veitur and RARIK. EFLA handled the main design, Borgarverk ehf. was the main contractor and Verkís provided construction supervision.

Borgarverk’s bid was ISK 242 million

Three bids were submitted when the roadworks were tendered in spring 2025.

Borgarverk submitted the lowest bid, at ISK 242,034,845, equivalent to 106.6% of the client’s cost estimate of ISK 226,920,100. Fagurverk bid ISK 299.3 million and Þróttur ISK 274.6 million.

Hvalfjarðarsveit’s municipal council approved entering into a contract with Borgarverk in June 2025, subject to the tender’s qualification requirements being met.

Borgarverk’s bid was therefore approximately ISK 15.1 million, or 6.6%, above the cost estimate.

The available project-closeout minutes do not state the final settlement cost. It is therefore not possible to assume that the final cost was the same as the original bid price.

More than 3,200 square metres of asphalt

The tender issued by Hvalfjarðarsveit, RARIK and Veitur covered extensive road construction and utility works.

The contract included, among other things, soil replacement for roads, sewerage, water mains, Veitur district-heating pipes, conduits, ducts and poles for street lighting, Hvalfjarðarsveit telecommunications infrastructure and RARIK electrical installations.

Borgarverk was also required to pave roads and pavements, cast kerbs, install dropped crossings with tactile paving and guidance lines for pedestrians, and erect traffic signs.

The principal quantities in the tender were:

  • 11,688 cubic metres of excavation
  • 12,272 cubic metres of fill
  • 3,218 square metres of asphalt
  • 1,561 metres of sewer pipes
  • 667 metres of water mains
  • 778 metres of district-heating pipes

Verkís provided supervision for ISK 6.5 million

A price survey for construction supervision was conducted alongside the project tender.

Two bids were received. COWI bid ISK 8.86 million, while Verkís bid ISK 6,536,040. The Infrastructure and Construction Committee recommended entering into a contract with Verkís, which subsequently supervised the works together with Hvalfjarðarsveit’s project manager for construction and assets.

EFLA designed the road network

The design of Melahverfi III had previously been tendered separately.

Four bids were submitted for the road design. EFLA submitted the lowest bid, at ISK 13,396,369. The other bids came from Hnit, COWI and VSÓ Ráðgjöf.

In December 2024, the municipal council approved a contract with EFLA for the road design. Contracts were also made with T.S.V. ehf. for preparing plot plans and with Snerra ehf. for designing the telecommunications infrastructure.

Road construction on Urðarmel and Holtamels

The construction permit covered, among other things, roads and utility infrastructure along sections of Urðarmel and Holtamels.

Hvalfjarðarsveit’s municipal council confirmed the construction permit in summer 2025, with Borgarverk registered as the contractor. The project complied with the applicable municipal master plan and local development plan for Melahverfi III.

The local development plan for the third phase of Melahverfi covers approximately 8.2 hectares of new residential land east of the existing settlement and provides for up to 68 homes. The objective is to offer a diverse range of housing and create a continuous urban area.

In June, a boundary description was also approved for the first 12 of 28 plots on Urðarmel.

Completion originally scheduled for December 2025

When the project was tendered in May 2025, full completion was scheduled for 31 December 2025.

However, the Infrastructure and Construction Committee first confirmed at its meeting on 22 September 2026 that the roadworks had been completed. The minutes do not state why completion took place later than the original tender schedule indicated.

Project details

  • Clients: Hvalfjarðarsveit, Veitur and RARIK
  • Main contractor: Borgarverk ehf.
  • Borgarverk’s bid: ISK 242,034,845
  • Tender cost estimate: ISK 226,920,100
  • Main design: EFLA
  • Construction supervision: Verkís
  • Telecommunications design: Snerra ehf.
  • Plot plans: T.S.V. ehf.
  • Confirmed completion: September 2026

An earlier BYGGINGAR.IS report dated 26 May 2025 covered the tender issued by Hvalfjarðarsveit, RARIK and Veitur for Melahverfi III.

Originally published in Icelandic on BYGGINGAR.IS.