Borgarverk ehf. submitted the lowest bid when Iceland’s Road and Coastal Administration opened tenders on 23 September 2026 for the construction of Búðafoss Road between Þjórsárdalsvegur and Landvegur, together with a new 204-metre bridge over the Þjórsá river.
Five bids were received. Borgarverk’s bid totalled ISK 2,532,331,206, equivalent to 87.1% of the Road and Coastal Administration’s estimated contract cost of ISK 2,908,407,213. The bid is therefore approximately ISK 376 million below the estimate.
Four bids exceeded the cost estimate
Borgarverk was the only company to bid below the estimated contract cost. The other four bids ranged from 5% to 23% above the estimate.
The difference between the lowest and second-lowest bids was just over ISK 520.7 million, while the gap between the lowest and highest bids was more than ISK 1.0 billion.
7.4-kilometre road and 204-metre bridge over the Þjórsá
The project is one of the largest road construction projects currently under way in South Iceland.
Búðafoss Road will be approximately 7.4 kilometres long, running from Þjórsárdalsvegur in Skeiða- og Gnúpverjahreppur across the Þjórsá to Landvegur in Rangárþing ytra.
The project includes a new 204-metre bridge over the Þjórsá, northeast of Búðafoss. A paved roundabout will also be built at the junction of Þjórsárdalsvegur and Búðafoss Road, together with connecting roads and access roads at four locations, totalling approximately 2.6 kilometres.
The works will also include two steel-plate riding tunnels, culverts, livestock underpasses, fences, cattle grids, lighting columns and other road equipment.
230,000 cubic metres of fill
The project involves extensive earthworks. According to the tender documents, the works include:
- 230,000 m3 of fill
- 50,000 m3 of subbase reinforcement material
- 38,000 m3 of base course
- 57,000 m2 of surface dressing
- 370 metres of culvert pipes
- 705 metres of guardrails
The bridge works include approximately 940 metres of drilled steel piles, 321 tonnes of steelwork and 173 precast units.
Tender deadline extended because of technical problems
Bids were originally due on 22 September, but the Road and Coastal Administration extended the deadline by 24 hours because of technical difficulties related to the tender.
The new deadline expired at 14:00 on 23 September, and the bids were published the same day.
The tender is numbered 24-029 and was originally advertised on 17 July.
Búðafoss Road expected to transform regional connections
The new road will connect Þjórsárdalsvegur and Landvegur across a new crossing of the Þjórsá, creating a direct transport link between Árnes and Rangárþing.
Skeiða- og Gnúpverjahreppur’s housing plan states that Búðafoss Road and the new bridge over the Þjórsá are expected to open in 2028. The municipality says the project will significantly improve transport connections and create opportunities for economic development in the area.
Project details
- Client: Iceland’s Road and Coastal Administration
- Tender: 24-029 – Búðafoss Road (23), Þjórsárdalsvegur–Landvegur
- Lowest bid: Borgarverk ehf., ISK 2,532.3 million
- Cost estimate: ISK 2,908.4 million
- Difference: ISK 376.1 million below the estimate
- Length of new road: approximately 7.4 kilometres
- New bridge over the Þjórsá: 204 metres
- Bids opened: 23 September 2026