The final foundation for the wind turbines at Vaðölduver was poured on Friday, 2 October, marking the completion of a major phase of the project. Fourteen wind turbines have already been erected, with the remaining 14 scheduled for installation in 2027.
More than a year of foundation work
The first foundation at Vaðölduver was poured in September 2025. Work on the foundations therefore continued for more than a year, alongside the transportation and installation of the wind turbines.
Coordinating these different work packages required close collaboration between contractors and personnel working on site. The pouring of the final foundation completes this major phase of the construction project.
Precision work from the ground up
The wind turbine foundations support the weight of the turbines and the forces generated as the wind drives their blades. Construction of each foundation includes excavation, sub-base preparation, reinforcement installation and the installation of tower anchors before the concrete is poured.
The work requires a high degree of precision. Utilities and other equipment connected to the wind turbine must be installed before the concrete is poured.
The tower anchoring equipment must be positioned accurately in both elevation and alignment so that the bottom section of the tower fits precisely during installation. Once the concrete work is complete, the concrete must reach the required strength before tower installation can begin.
Ístak carried out the civil works, while COWI supervised the project.
Fourteen wind turbines to be erected next year
Installation of the first 14 wind turbines was completed at the end of August. The remaining 14 are scheduled to be erected in 2027.
Vaðölduver is being developed east of the Þjórsá river and south of the Sultartangi Dam in Rangárþing ytra. Once complete, the wind farm will comprise 28 wind turbines with an installed capacity of approximately 120 megawatts.
Originally published in Icelandic on BYGGINGAR.IS.