A detached house in Hólar in Breiðholt was altered to create five flats without permission being sought.
The owners of a house in Hólahverfi in Reykjavík were unsuccessful when they asked the Reykjavík building official to grant permission for work that had already been carried out. Five new flats had been created in the detached house, which was built in 1973.
The owners said the house had been altered in 1998, but the building official said that because no permission had been granted for the alterations and they exceeded the permitted development, the house would have to be restored to its previous state. This was to be done within 60 days, otherwise the owners would face daily fines.
The owners did not accept this and appealed the decision to Úrskurðarnefnd umhverfis- og auðlindamála (the Environmental and Natural Resources Board of Appeal).
From 287 square metres to 430
The Board of Appeal’s consideration states that, based on the size of the plot and the permitted plot ratio, the house may be no larger than 287 square metres. Drawings now indicate that it has grown to 429.5 square metres after the basement was excavated and converted into flats. Planning rules had also allowed for one additional flat, but there are now five.
Four flats were created in the basement and one in the garage.
The owners said they could not restore the property to its previous state within the time they had been given. They pointed out that they had indefinite tenancy agreements with tenants, including clients of Reykjavíkurborg (the City of Reykjavík) social services. Those agreements would have to be terminated with at least 12 months’ notice. They also said it would not be possible to carry out all the alterations required by the building official within 60 days.
Deadline too short
The Board of Appeal overturned the deadline in the building official’s decision. It said it was appropriate to take into account the scale of the work that would be required and the fact that the flats were rented out and subject to statutory notice periods. The Board therefore found that the 60-day deadline did not comply with the principle of proportionality and overturned the deadline.
The Board also pointed out to the owners that they could apply for a building permit for alterations to the basement, as such a permit had been granted for another house on the same street. In both cases, foundation space had been excavated to create basement space.
Bicycle shelter allowed to remain
The Board of Appeal also rejected a claim by the owner of another property who objected to a bicycle shelter on the neighbouring plot not being removed. It was built without any permission several years ago, behind commercial premises in Skipholt. The building official considered that, because the bicycle shelter was more than 20 metres from commercial premises on Laugavegur, there was little risk of fire spreading between the buildings and that safety and public-interest considerations did not require the shelter to be removed.
Source: Ruv.is