Kópavogur municipality plans to seek full compensation from contractor Rizzani de Eccher for breaches of contract during the construction of Kársnes Primary School. The claim is for nearly ISK 3.9 billion.

This was announced by Kópavogur municipality. In 2021, the municipality signed an agreement with the Italian construction company to rebuild the school at Skólagerði. Kársnes Primary School is now operated as a combined preschool and primary school.

The municipality had estimated the project at ISK 4.8 billion when it was put out to tender in 2020, equivalent to ISK 6.7 billion in current value. The contract amount was ISK 3.2 billion, and the work was due to be completed by 15 May 2023.

The contract was terminated in 2023 because of “serious breaches of contract.” The project should have been handed over at that point, but was only half-finished. The contractor had been paid ISK 2 billion in current-value terms.

“In addition to the delays, Kópavogur municipality had serious concerns about the quality of the work, as the structure had been left exposed to the weather. It had also become clear that subcontractors had stopped working. The defects in the project proved extensive and also caused major delays. The construction period, which was supposed to be just over two years, became five years, with the resulting inconvenience and costs,” the municipality said.

The project has now been completed in full, at a total cost of ISK 8.7 billion—ISK 2 billion above the municipality’s cost estimate. The additional cost is largely attributed to the breaches described above.

“In recent months, Kópavogur municipality has been compiling its claim and supporting documentation for the additional costs incurred as a result of changing contractors, delays and extensive defects in the project,” the announcement said.

The claim was presented to the arbitration tribunal and the municipal executive committee this week. It amounts to nearly ISK 3.9 billion, and the municipality is demanding that the contractor pay the full cost.