Executives from two construction companies interviewed by Spegillinn have criticised how planning has been handled in the Reykjavík capital area. They say housing has not been built in line with demand.
As reported by Spegillinn last week, around 1,900 newly built and completed homes are standing empty—85% more than a year ago. Many have been on the market for a full year.
Unemployment in construction and civil engineering is rising, and there are cases of strong companies significantly scaling back their operations. This week, it was also reported that ÍAV, one of Iceland’s largest contractors, had laid off 20 employees.
According to an analysis by the Federation of Icelandic Industries, the total number of unemployed people in construction and civil engineering was 1,106 in August. That was an increase of 260, or just over 30%, from the same month the previous year.
Residential construction accounts for around one-third of the sector
Construction and civil engineering can be divided into three areas. According to information from the Federation of Icelandic Industries, residential construction accounts for around 35% of sector turnover, commercial buildings for 40% and public infrastructure projects for 24%. The contraction is particularly pronounced in the residential construction segment.
Jón Bjarni Jónsson, chairman of Byggiðn, the construction workers’ union, is concerned about the new-build housing market. The market has cooled considerably, he says, and the union is handling a significant number of cases related to redundancies.
At larger companies, workers have been laid off in small groups that do not necessarily qualify as collective redundancies. Small companies may have laid off around five people—but that may represent their entire workforce.
Compared with May, June and July 2025, unemployment in the construction sector has risen by 27–33%. The figures do not include foreign workers who lose their jobs and return home. “These are staggering figures,” Jón Bjarni says.
‘I want to call for the government’
Jón Bjarni says he knows of a case involving a strong and large construction company that has substantially reduced its operations by cutting its workforce. Key employees who had worked for the company for many years have even lost their jobs.
Other signs of contraction include more companies falling behind on pension-fund payments, while the number of bankruptcies has also increased. He says the situation is serious and uncertainty is likely to continue growing.
“I want to call for the government. We are heading into a very serious situation,” he says. Trade unions have sat down with the Confederation of Icelandic Enterprise to discuss the continuation of collective agreements, but the government is missing from the table.
All economic indicators are pointing in the same direction. Turnover in the construction market is declining, while imports of construction materials have fallen by nearly one-quarter from last year. Companies in the sector are also falling substantially further behind on payments. The rate was around 3% at the end of last year but had risen to around 6% by this summer.
Supply does not match the market
Einar Páll Kjærnested, sales manager at Byggingafélagið Bakki, says the situation in the new-build market is difficult. The main problem, he says, is that the supply of properties does not meet the needs of the market.
Market surveys show that people are looking for housing that is very different from what has mainly been built in the capital area over the past decade.
He says the development of the built environment changed fundamentally with the capital-area regional plan approved in 2015. Since then, more than 90% of all new development has been in apartment buildings, while surveys show that only 50–60% of people actually want to live in such buildings.
However, he says that is not the biggest problem. More than 80% of apartment buildings under construction are large—that is, buildings with more than 16 apartments.
Surveys show that people who want to live in apartment buildings prefer small ones, perhaps with five to eight apartments, rather than buildings with 50–100 units such as those now being built.
Difficulty finding suitable sites
In recent months, Byggingafélagið Bakki has been building the fourth phase of the Helgafell neighbourhood, a mixed development consisting primarily of small, two-storey apartment buildings.
In cooperation with the Housing and Construction Authority, HMS, and the municipality of Mosfellsbær, the company has also built a 30-unit apartment building specially designed for young people and those with limited assets. Half of the apartments went to people eligible for equity loans, and 80% went to first-time buyers.
Einar says the homes built by the company have sold well. So far, everything has sold in less than two months. The company has not experienced slow sales, he says. The explanation is simply that it has built the type of housing the market is seeking.
At the same time, the company is having difficulty finding sites for its next projects because all available plots are planned for large apartment buildings.
More expensive to build on infill sites
Einar says it is impossible to build inexpensive or cost-effective homes on infill sites. In the aforementioned apartment building in Mosfellsbær built by Bakki, 16 square metres of common space had to be built for every 100-square-metre apartment.
On infill sites, around 60 square metres of common space—mostly for underground parking—must be built for an apartment of the same size, making the project considerably more expensive.
Einar believes the winter will be very difficult for construction companies in the middle of projects that are hard to slow down. “I don’t know how people intend to persuade the public to move into large apartment buildings that people do not want to move into.”
Planning philosophy needs to change
He says municipalities in the capital area should use the winter to review the capital-area regional plan. The planning philosophy needs to change, he says.
Development can be more concentrated where that makes sense, such as near the city centre, while development should be allowed to be more dispersed on the outskirts of the capital area. There is ample land in Kjalarnes, South Iceland and West Iceland.
The problem, Einar says, is that municipalities are so dependent on infrastructure revenues from new projects. “They just want to build densely because that gives them the most revenue. Until now,” he says.
Asked whether this approach would not create traffic congestion everywhere if development were pushed towards the outskirts, Einar says workplaces must be located in more places than just the centre of the area. That would allow traffic to be distributed more widely.
Difficult conditions with no clear improvement ahead
JÁVERK is one of Iceland’s largest construction companies. It has a mixed operation, working both in the tender market and on projects developed on its own initiative.
Gylfi Gíslason, the company’s managing director, says conditions in the new-build market are difficult and that the outlook is not necessarily bright.
Inflation, high interest rates and the Central Bank’s borrower-based lending requirements have caused sales to slow. Companies whose main business is building homes have significant amounts of capital tied up in unsold properties, meaning that new projects are not getting under way. The most important task is to bring down inflation and, consequently, interest rates.
‘Not the best time for the state to increase taxation’
Taxation of the sector has also been steadily increasing. Municipalities have realised that they went too far in imposing taxes on residential development.
“But then the state comes along and adds to it,” Gylfi says, pointing to the government’s budget bill, which proposes tax increases by reducing VAT reimbursements for work carried out on construction sites.
That would increase the cost of a 100-square-metre home by an average of ISK 1.5 million. The reimbursement was also reduced towards the end of the previous parliamentary term, which increased costs by ISK 2.5–3 million.
“This is not the best time, one would think, to increase taxation on residential property.”
Slow sales, but not a standstill
Gylfi says the company has not slowed projects that have already started, as doing so would be expensive. On the other hand, it is in no hurry to begin new projects.
The company has around 100 unsold homes in the capital area and nearby communities. “It is not a standstill, let that also be said, but things are simply happening more slowly.”
Fortunately, the company has not had to lay off employees, and its good workload on projects for third parties has helped.
It is sometimes said that construction-market performance has been good and that contractors made strong profits during the boom of recent years. Gylfi was asked about this and whether contractors should not have sufficient reserves to deal with the current conditions.
He pointed out that the sector is cyclical, with both good and bad years. After-tax margins for companies building commercial properties have been between 5% and 7%. That would not necessarily be considered good in other industries. Turnover is high, but construction companies also take substantial risks.
‘Far more mistakes made in planning than before’
Gylfi says it is clear that municipal planning takes insufficient account both of people’s housing preferences and of changes in the age composition of the population.
Requirements imposed by municipalities regarding the average size of apartments in apartment buildings have also resulted in too few small apartments being built. Too many large apartments are being built, and they are not selling. He has tried to obtain permission to build more small apartments, but that request was rejected.
The past few years have been one of the strongest periods of residential construction in Iceland’s history. It was clear that activity would slow, he says, but the cycle is now being amplified.
“And I think we have made far more mistakes in planning than before,” says Gylfi Gíslason, managing director of JÁVERK.
Originally published in Icelandic on BYGGINGAR.IS.