ÞG Verktakar submitted the lowest bid when Iceland’s Road and Coastal Administration, Vegagerðin, opened tenders on 29 September for the construction of a new section of Westfjords Road through Gufudalssveit, between Skálanes and Hallsteinsnes.
ÞG Verktakar bid ISK 3,888,451,476, equivalent to 159.9% of Vegagerðin’s estimated contractor cost of ISK 2,431,870,289. The bid is therefore approximately ISK 1.46 billion above the estimate.
Only two bids were received. Ístak hf. offered ISK 5,992,459,407, or 246.4% of the estimated cost. The difference between the two bids is just over ISK 2.1 billion.
Both bids significantly above estimate
The bids were as follows:
- ÞG Verktakar: ISK 3,888,451,476, or 159.9% of the estimated contractor cost.
- Ístak hf.: ISK 5,992,459,407, or 246.4%.
- Estimated contractor cost: ISK 2,431,870,289.
ÞG Verktakar’s bid is therefore approximately 59.9% above the estimate, while Ístak’s bid is 146.4% above it. The opening of the bids does not mean that a contract has been awarded; Vegagerðin will now review the tenders.
4.6-kilometre new road across Djúpafjörður and Gufufjörður
The project involves constructing approximately 4.6 kilometres of Westfjords Road across Djúpafjörður and Gufufjörður.
The largest individual structure is a 210-metre network arch bridge across Djúpafjörður, with a concrete bridge deck.
The project is one of the final major stages in the reconstruction of Westfjords Road through Gufudalssveit. Once this section is open, the route through the area will be shortened by approximately 16 kilometres and will also bypass Ódrjúgsháls.
865 tonnes of steel for the bridge
The project is extensive in terms of both road construction and bridge building. The tender documents provide for, among other works:
- 31,100 cubic metres of rock excavation
- 55,900 cubic metres of fill
- 20,900 cubic metres of sub-base reinforcement material
- 9,200 cubic metres of base course
- 39,300 square metres of surface treatment
- 6,150 metres of guardrails
The bridge will require, among other materials, 865 tonnes of steel for the superstructure, 48 tonnes of hanger rods and surface treatment for approximately 4,500 square metres of steelwork.
According to the tender specifications, the bridge deck will include 252 precast units, 420 cubic metres of in-situ concrete and 87 tonnes of reinforcing steel.
Part of a 25.8-kilometre reconstruction of Westfjords Road
The wider Gufudalssveit project covers approximately 25.8 kilometres of new road and is expected to eliminate four single-lane bridges. According to Vegagerðin, the project will shorten the overall route by approximately 21.6 kilometres.
The project has been carried out in several stages in recent years.
Borgarverk, for example, completed the fills between Hallsteinsnes and Skálanes during 2023–2025. That stage involved approximately 3.6 kilometres of new road and a 119-metre temporary bridge across Gufufjörður.
Construction is also under way on a 58-metre bridge across Djúpafjörður at Grónes and an approximately 130-metre bridge across Gufufjörður. The work is being carried out by Norwegian company Leonhard Nilsen & Sønner, with completion scheduled for 30 September 2026.
Completion scheduled for October 2028
The Skálanes–Hallsteinsnes tender was advertised on 10 June, and the deadline for bids was 14:00 on 29 September.
According to the tender documents, the project must be fully completed by 1 October 2028.
- Client: Vegagerðin
- Tender: 26-093
- Project: Westfjords Road (Route 60) through Gufudalssveit, Skálanes–Hallsteinsnes
- Lowest bid: ÞG Verktakar, ISK 3,888,451,476
- Cost estimate: ISK 2,431,870,289
- Difference: approximately ISK 1.46 billion above the estimate
- Road length: approximately 4.6 kilometres
- Network arch bridge: 210 metres
- Scheduled completion: 1 October 2028
Originally published in Icelandic on BYGGINGAR.IS.